Permit Reef · one-page route summary
The California shellfish and seaweed permitting route
The same review steps shown on the Permit Tracker, in the same order. Time and fee ranges are compiled estimates drawn from published agency pages and published reports, not quotes. Nothing here is filed for you, and nothing here is legal advice.
For your own project, answer four questions and print just the steps that apply. The same steps are also published as a read-only feed at /api/public/route-map.json.
This page is a printable summary of the Permit Tracker, compiled from published agency pages. Covers California shellfish and seaweed only. Every outside link on this page was last checked automatically on Sep 18, 2026, and it is re-checked weekly. The agency's own published page and notice remain the legal record.
- STEP 1
Siting & lease
Who may hold water, and on what terms.
CA Fish & Game Commission (CFGC) STATE
Lease approval and public-interest determination (FGC §15400). CDFW staff administers the four-phase application; the Commission grants the lease.
Applies to: New lease · renewal · species change · Published time range: 12–36 months · Published fee range: $1.5K–$10K
https://fgc.ca.gov/Checked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfState Lands Commission STATE
Tidelands and bottom lease interest where the site sits on state sovereign land.
Applies to: New lease · renewal · Published time range: 12–24 months · Published fee range: $1K–$8K + rent
https://www.slc.ca.gov/Agency page link checked Sep 18, 2026Harbor / port district LOCAL
Where a district holds granted tidelands (Humboldt Bay, San Diego), the district is the leasing and CEQA lead agency.
Applies to: Pre-permitted footprint · Published time range: 3–9 months · Published fee range: Varies
https://humboldtbay.org/development-permitsAgency page link checked Sep 18, 2026
- STEP 2
Environmental review
The analysis that has to exist before a decision can be made.
CEQA lead agency STATE
Initial Study, then a Negative Declaration or EIR. The lead is CFGC for state leases, or the district/county where they hold the approval.
Applies to: Most new and amended projects · Published time range: 12–48 months · Published fee range: $60K–$250K consultant
https://opr.ca.gov/ceqa/Agency page link checked Sep 18, 2026California Coastal Commission STATE
Coastal development permit or federal consistency determination.
Applies to: Coastal zone projects · Published time range: 12–24 months · Published fee range: $2K–$15K
https://www.coastal.ca.gov/Checked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfTribal consultation TRIBAL
AB 52 and SB 18 where triggered; in the Chumash Heritage NMS zone, ONMS §304(d) co-stewardship applies. Permit Reef treats this as partnership, not a checkbox.
Applies to: Where triggered by location · Published time range: 3–12 months · Published fee range: —
https://nahc.ca.gov/Checked Sep 18, 2026 · the page did not answer our automatic check, so open it yourself
- STEP 3
Water & federal
Water quality, navigation, and protected species.
Regional Water Board (RWQCB) STATE
Section 401 water quality certification; waste discharge requirements for land-based systems.
Applies to: All in-water and discharging projects · Published time range: 6–18 months · Published fee range: $500–$5K
https://www.waterboards.ca.gov/waterboards_map.htmlAgency page link checked Sep 18, 2026USACE FEDERAL
Section 10 / 404 authorization for structures and work in navigable waters.
Applies to: All in-water structures · Published time range: 12–36 months · Published fee range: Free–$100
https://www.spn.usace.army.mil/Missions/Regulatory/Checked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfNOAA Fisheries (NMFS) & USFWS FEDERAL
ESA and MMPA consultation, essential fish habitat review.
Applies to: Where listed species or habitat occur · Published time range: 6–24 months · Published fee range: Free
https://www.fisheries.noaa.gov/west-coast/consultations/esa-section-7-consultations-west-coastAgency page link checked Sep 18, 2026
- STEP 4
Food safety & product
What has to be true before anyone eats it.
CDPH — shellfish sanitation STATE
NSSP growing-area classification, harvest controls, certification, and tagging for bivalves.
Applies to: All bivalve shellfish · Published time range: 3–9 months · Published fee range: $1K–$5K
https://www.cdph.ca.gov/Programs/CEH/DRSEM/Pages/EMB/Shellfish/Shellfish-Program.aspxChecked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfCDPH — processed food registration STATE
Processed Food Registration and HACCP where processing occurs. Seaweed as a food sits on partly unsettled ground — see Known Gaps.
Applies to: Seaweed and processed product · Published time range: 2–6 months · Published fee range: $500–$2K
https://www.cdph.ca.gov/Programs/CEH/DFDCS/Pages/FDBPrograms/FoodSafetyProgram/ProcedureObtainingProcessedFoodRegistration.aspxChecked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfCounty environmental health LOCAL
Facility, water supply, and handling review for shoreside and upland operations.
Applies to: Land-based and processing · Published time range: 1–6 months · Published fee range: Varies
https://www.ccdeh.com/Checked Sep 18, 2026 · the page did not answer our automatic check, so open it yourself
- STEP 5
Operate & keep current
The part that never ends.
CDFW — annual registration STATE
Aquaculture registration for every facility, every year (FGC §15101, 14 CCR §235, form DFW 750).
Applies to: Every operation, every year · Published time range: 1–3 months · Published fee range: ~$500 base
https://wildlife.ca.gov/Conservation/Marine/AquacultureChecked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfCDFW — stock movement & health STATE
Importation, transfer, and disease inspection approvals for seed, spore, and broodstock.
Applies to: Any stock movement · Published time range: 1–4 months · Published fee range: Varies
https://wildlife.ca.gov/Conservation/Marine/AquacultureChecked Sep 18, 2026 · the page did not answer our automatic check, so open it yourselfLocal use permit LOCAL
County or city use permit, plus lease-condition reporting and monitoring obligations.
Applies to: Most shoreside footprints · Published time range: 3–12 months · Published fee range: Varies widely
https://opr.ca.gov/planning/general-plan/Agency page link checked Sep 18, 2026
Permit Reef charts the route and gathers what is published. It does not file anything, does not give legal advice, and does not speak for any agency. The agency's own notice remains the legal record. Coverage is California shellfish and seaweed only.